- Design Development Submittal This step shall contain a complete set of all progress plans and specifications, construction documents and fire and life safety and MEP narrative, with sufficient details and dimensions to ascertain whether basic criteria is being incorporated and shall be submitted to Hyatt at the milestones indicated below. The design development documents will include at minimum the following items, without limitation.
- Architectural Drawings
- Interior Design Drawings
- Landscape Drawings
- Pool / Water Feature Drawings (if applicable)
- Lighting Design Drawings
- MEP Drawings
- FLS Drawings
- IT Drawings
- A/V Drawings
- Keyed Food Service Equipment Plans and Elevations
- Keyed Laundry Equipment Plans and Elevations
- Sketches as required
- System Schematics
- Schedules and Specifications (inclusive of BOH areas)
- Material Samples and Specifications (inclusive of BOH areas)
- FF&E layouts (inclusive of BOH areas)
- FF&E Samples and Specifications. (inclusive of BOH areas)
- Exterior Signage Drawings
Unacceptable designs or incomplete submittals may need to be resubmitted. Hyatt will issue a formal review prior to moving onto the next step. A 50% design development presentation and 100% design development document submittal shall be submitted by Franchisee or its Consultants according to the deadlines specified by Hyatt for the Project.
Source: Item 18 — OTHER INCOME (LOSS), NET (FDD pages 187–399)
What This Means (2025 FDD)
According to The Standardx's 2025 Franchise Disclosure Document, the second submittal required in the Design Review Submittal Process is the Design Development Submittal. This submittal should contain a complete set of all progress plans and specifications, construction documents and fire and life safety and MEP narrative, with sufficient details and dimensions to ascertain whether basic criteria is being incorporated.
The design development documents must include, at a minimum, architectural drawings, interior design drawings, landscape drawings, pool/water feature drawings (if applicable), lighting design drawings, MEP drawings, FLS drawings, IT drawings, A/V drawings, keyed food service equipment plans and elevations, keyed laundry equipment plans and elevations, sketches as required, system schematics, schedules and specifications (inclusive of BOH areas), material samples and specifications (inclusive of BOH areas), FF&E layouts (inclusive of BOH areas), and FF&E samples and specifications (inclusive of BOH areas), and exterior signage drawings.
The Standardx requires that unacceptable designs or incomplete submittals may need to be resubmitted. The Standardx will issue a formal review prior to moving onto the next step. Franchisees or their consultants must submit a 50% design development presentation and a 100% design development document submittal according to the deadlines specified by The Standardx for the Project.