What is the dependency between the approval of the Site and the submission of Construction Plans for a Creative World School?
Creative_World_School Franchise · 2025 FDDAnswer from 2025 FDD Document
nd parking layout, and Operating Assets which include fixtures, equipment, signs, and furnishings. However, you are obligated to have prepared, at your expense, all required Construction Plans and specifications to suit the shape and dimensions of the Site and to ensure that such plans and specifications comply with applicable ordinances, building codes and permit requirements and with lease requirements and restrictions. You agree to submit Construction Plans and specifications to us for approval before construction of the School is commenced, and within 120 days of the date we approved your Site and, at our request, submit all revised or "as built" plans and specifications during the course of such construction. We will approve or disapprove your Construction Plans within 60 days of the date you provide complete Construction Plans to us. The date of our approval of the Construction Plans is referred to as the "Construction Approval Date." Once approved by us, the Construction Plans may not be modified or altered without our prior approval. Your Construction Plans must include an estimated schedule of Construction Activities, architectural plans, land use plans and the like. If we deem it necessary or appropriate, we may grant you up to 3 additional 30-day extensions to permit you to meet the schedule for Construction we approve in your Construction Plans.
Source: Item 23 — RECEIPTS (FDD pages 80–247)
What This Means (2025 FDD)
According to the 2025 Creative World School FDD, a franchisee must first have their proposed site approved by Creative World School before submitting construction plans. Specifically, the franchisee has 120 days from the date of site approval to submit their construction plans for the location. The construction plans must be suited to the site's shape and dimensions, comply with local ordinances, building codes, permit requirements, and lease restrictions.
Creative World School will provide prototype design plans, specifications, decor, and layout for a school, including requirements for design, color scheme, image, interior and exterior layout, playground and parking layout, and operating assets. The franchisee is responsible for having the required construction plans and specifications prepared at their own expense.
Creative World School will then approve or disapprove the construction plans within 60 days of receiving the complete construction plans from the franchisee. The date Creative World School approves the construction plans is termed the "Construction Approval Date." Once approved, the construction plans cannot be modified without prior approval from Creative World School.