What is the 'Opening Deadline' for a Chicken Guy franchise, and where is it specified?

Chicken_Guy Franchise · 2025 FDD

Answer from 2025 FDD Document

Notwithstanding the occurrence of any events, except events constituting Force Majeure, construction shall be completed, and the Franchised Restaurant shall be furnished, equipped and shall otherwise be ready to open for business in accordance with this Agreement not later than the date specified in the attached Data Sheet ("Opening Deadline").

Source: Item 22 — CONTRACTS (FDD page 50)

What This Means (2025 FDD)

According to Chicken Guy's 2025 Franchise Disclosure Document, the 'Opening Deadline' is the date specified in the attached Data Sheet. Franchisees must ensure the restaurant is fully furnished, equipped, and ready to open for business by this date, as stated in Item 22 of the FDD.

Chicken Guy may extend the Opening Deadline if delays occur due to events constituting Force Majeure, which includes acts of God, strikes, war, riots, epidemics, fires, governmental actions, or other causes beyond the franchisee's control. If such events delay the commencement of construction, Chicken Guy will proportionately extend the deadline.

Failure to open the Franchised Restaurant by the Opening Deadline, without an approved extension, can result in the termination of the Franchise Agreement. Therefore, it is crucial for prospective Chicken Guy franchisees to carefully review the Data Sheet attached to the Franchise Agreement to understand their specific Opening Deadline and to proactively manage construction and preparation to meet this critical milestone.

Disclaimer: This information is extracted from the 2025 Franchise Disclosure Document and is provided for research purposes only. It does not constitute legal or financial advice. Consult with a franchise attorney before making any investment decisions.