For Caption By Hyatt franchises, what critical milestones for IT Systems are dependent on?

Caption_By_Hyatt Franchise · 2025 FDD

Answer from 2025 FDD Document

Critical milestones for IT Systems are dependent on available electricity, conduit, core drilling and cabling in the Computer Room, Gallery Host Stand, E-room, Meeting Rooms, etc. Every effort will be taken to schedule computer system vendors without change or expedite fees since this will add to the cost of the Project.

8. Completion Criteria

This Statement of Work will be deemed completed when:

  • the Computer Room installed and operational;
  • the Gallery Host Stand installed and operational;
  • the Hyatt Standard IT Systems are installed an operational; and
  • completion of Vendor training.

Source: Item 22 — Contracts (FDD page 85)

What This Means (2025 FDD)

According to Caption By Hyatt's 2025 Franchise Disclosure Document, the critical milestones for IT systems are dependent on several infrastructural elements being in place. Specifically, the availability of electricity, conduit, core drilling, and cabling in key areas such as the Computer Room, Gallery Host Stand, E-room, and Meeting Rooms are crucial for the successful implementation of IT systems. This dependency highlights the importance of coordinating the IT setup with the construction and infrastructure development phases of the project.

Caption By Hyatt emphasizes the need to schedule computer system vendors efficiently to avoid incurring change or expedite fees, as these would increase the overall project cost. This suggests that franchisees should proactively manage and coordinate with various vendors and contractors to ensure that the necessary infrastructure is ready in a timely manner. Effective project management is essential to keep costs under control and adhere to the planned budget.

The completion of the IT systems setup is formally marked by several criteria. These include the Computer Room being fully installed and operational, the Gallery Host Stand being installed and operational, and the Hyatt Standard IT Systems being installed and operational. Additionally, vendor training must be completed. These criteria serve as clear benchmarks for franchisees to track progress and ensure that all critical IT components are functioning correctly before the hotel opens.

Prospective Caption By Hyatt franchisees should pay close attention to these dependencies and completion criteria to ensure a smooth and cost-effective IT system implementation. Proper planning, coordination, and adherence to the franchisor's guidelines are vital for meeting these milestones and successfully launching the hotel's IT infrastructure.