How many days before the Opening Date must a Buff City Soap franchisee complete construction?
Buff_City_Soap Franchise · 2025 FDDAnswer from 2025 FDD Document
- (5) Franchisee will commence construction at least 120 days before the Opening Date as set forth in Exhibit G and will complete construction no later than 30 days before the Opening Date.
Construction will be deemed to have commenced upon the commencement of site work by heavy equipment, or in the event the Makery is to be located in existing shell space, commencement of construction-related work at the Premises.
Franchisee will advise Franchisor of commencement of construction within ten days of the commencement date.
Once construction has commenced at the Premises, it will continue uninterrupted until completed except for interruption by reason of a Force Majeure Event.
Source: Item 23 — Receipts (FDD pages 69–186)
What This Means (2025 FDD)
According to Buff City Soap's 2025 Franchise Disclosure Document, a franchisee must complete construction of their Makery no later than 30 days before the Opening Date. The franchisee is also required to commence construction at least 120 days before the Opening Date, as outlined in Exhibit G.
Construction commencement is defined as the start of site work using heavy equipment. If the Makery is located in an existing shell space, construction begins with the commencement of construction-related work at the premises. The franchisee must inform Buff City Soap of the construction start date within ten days of commencement.
Once construction begins, it must continue without interruption unless a Force Majeure Event occurs. This ensures that the Makery is completed in a timely manner, allowing for pre-opening activities and training to take place before the grand opening. This timeline is crucial for franchisees to manage their project effectively and coordinate with Buff City Soap for inspections and approvals.