How many days before the Opening Date must construction commence for a Buff City Soap franchise?
Buff_City_Soap Franchise · 2025 FDDAnswer from 2025 FDD Document
- (5) Franchisee will commence construction at least 120 days before the Opening Date as set forth in Exhibit G and will complete construction no later than 30 days before the Opening Date.
Construction will be deemed to have commenced upon the commencement of site work by heavy equipment, or in the event the Makery is to be located in existing shell space, commencement of construction-related work at the Premises.
Franchisee will advise Franchisor of commencement of construction within ten days of the commencement date.
Once construction has commenced at the Premises, it will continue uninterrupted until completed except for interruption by reason of a Force Majeure Event.
Source: Item 23 — Receipts (FDD pages 69–186)
What This Means (2025 FDD)
According to Buff City Soap's 2025 Franchise Disclosure Document, construction for a new location must begin at least 120 days before the scheduled Opening Date. The construction must then be completed no later than 30 days before the Opening Date.
Construction commencement is defined as the start of site work using heavy equipment. If the Buff City Soap location is in an existing space, construction begins when construction-related work starts at the premises. The franchisee is required to inform Buff City Soap of the construction start date within ten days of commencement.
Once construction begins, it must continue without interruption until completion, except in cases of a Force Majeure Event. This rigorous timeline ensures that the Buff City Soap makery is ready to open on schedule and meets the brand's standards for quality and presentation.